Decision Maker: Deputy Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To give approval to CNDCL to appoint Moody
Construction LTD to deliver Phase 3 of the Treadmills development
and to approve the
consequent increase in the Council's budget.
PDR Construction was appointed as contractor
to deliver Phase 3 of the Treadmills development. Work commenced on
site. On 11 January 2022, however, PDR appointed administrators. In
consequence, CNDCL (the Council's development partner) terminated
the contract with PDR on 19th January 2022. As a result, another
contractor is needed to continue with the delivery of Phase 3.
During CNDCL's original tender process, Moody Construction
Ltd
was placed second. Moody has now provided a revised tender for the
contract. The revised construction costs with Moody as principal
contractor result in an increase in the overall construction costs
for Phase 3. The increase reflects the rise in costs (occasioned by
inflation and market forces) between the date of the original
contract and the new tender. Using the contingency of the
Treadmills development budget and some underspend in other areas of
the development budget, means that this overspend can be broadly
met from within the development budget, however, there is an
overall increase to the Treadmills Development budget of some
£78,000. The increased contract price means that the costs of
development are no longer in accordance with the Council's approved
budget.
CNDCL has obtained advice from their Cost Consultant LHL, which
confirms that the increases in Moody's tender price is in line with
the current market conditions. LHL has also confirmed that the
revised tender establishes value for money. This is explained
further in the attached Value for Money assessment Note.
The decision is an urgent one and it is not practical to wait for a
quorate council to be convened. The reasons are as follows. Moody's
has provided a fixed price for the outstanding works needed for the
delivery of Phase 3, and at present is able to hold some of the
steelwork costs to that previously agreed with the steel fabricator
sub-contractor, notwithstanding that the costs of steel have
increased in the interim. However, following the end of the month
(31st January 2022), Moody's has advised that it would need to
revise its tender costs in order to incorporate any cost increases
from its subcontractors.
Another consideration is the need to appoint a new contractor as
quickly as possible. This will ensure that development is not
'stalled' for more than is necessary and will, as far as possible,
ensure that key development dates on site are adhered to. Also, of
consideration is that the development has secured a key anchor
tenant (Everyman Cinema). Should the development not be completed
in a timely manner (and any delay in appointing a new contractor
could adversely impact on delivery), then Everyman can terminate
the agreement. Further, construction costs are continuously rising
due to increased material and labour costs, and also due to the
uncertainties that the construction market faces. There is a window
of opportunity for Moody's to take over the construction quickly
and at a fixed price for now, but this will be at risk if the
decision is not made before the end of the month, both in terms of
costs and the possible availability of sub-contractors. It is not
practical to convene a meeting of council before that date.
Any relevant decisions by officers must only be taken where they
are in line with the Council's budget and policy framework. Any
decision
which is contrary to or not wholly in accordance with the budget
approved by full Council must be referred to the Council for final
decision. However, such a decision may be taken by relevant
officers if the decision is urgent, it is not practical to convince
a meeting of Council, and the Chairman of the Scrutiny Committee
agrees that the decision is a matter of urgency. This is the
situation in this case. Given the urgency in this decision, and the
consequences of not appointing the contractor quickly (for the
reasons set out), this urgent decision shall not be subject to the
call-in procedures as this would seriously prejudice the Council's
interests (e.g. by putting the development timetable at risk, the
likely further increase in costs, and subsequent reputational
damage), and prejudice the public interest (e.g. the risk that
delivery of Phase 3 may be further delayed with risks to the
provision of the cinema, increased costs and potential loss of
funding).
CNDCL carrying out a full retendering exercise
for the contract has been considered and rejected. Another option
of 'mothballing' the site risks both loosing Everyman as a tenant
and the Future High Street Funding of £4.75m already secured
for this development and which is subject to delivery
targets.
Declarations: None
Dispensations in respect of Executive Members: None
Contact: Mick Jewitt, Deputy Chief Executive Email: mick.jewitt@hambleton.gov.uk.
Publication date: 31/01/2022
Date of decision: 28/01/2022
Accompanying Documents: