2015/16 Quarter 3 Capital Programme and Treasury Management Monitoring

Meeting: 09/02/2016 - Cabinet (Item 52)

52 2015/16 Quarter 3 Capital Programme and Treasury Management Monitoring pdf icon PDF 69 KB

The purpose of this report is to provide the Quarter 3 update at 31 December 2015 on the progress of the Capital Programme 2015/16 and the Treasury Management position.  A full schedule of the Capital Programme 2015/16 schemes is attached at Annex ‘A’ of the report, together with the relevant update on progress of each scheme.

 

In accepting the recommendations, Cabinet will approve and recommend to Council the net decrease of £3,047,453 in the Capital Programme to £14,237,403 as detailed in Annex ‘B’ and also in the Capital Programme attached at Annex ‘A’ of the report; the increase of capital expenditure funded from the Economic Development Fund of £168,996; the funding allocation to the capital programme as detailed in paragraph 3.1 and the Treasury Management position and prudential indicators at Annex ‘E’.

Additional documents:

Minutes:

The subject of the decision:

 

This report provided the Quarter 3 update at 31 December 2015 on the progress of the Capital Programme 2015/16 and the Treasury Management position.  A full schedule of the Capital Programme 2015/16 schemes was attached at Annex A of the report, together with the relevant update on progress of each scheme.

 

Alternative options considered:

 

None.

 

The reason for the decision:

 

To comply with the requirements of the Local Government Act 2003 and the Chartered Institute of Public Finance and Accountancy (CIPFA) Prudential Code and the CIPFA Treasury Management Code of Practice.

 

THE DECISION:

 

That Cabinet approves and recommends that Council approves:-

 

(1)     the net decrease of £3,047,453 in the Capital Programme to £14,237,403 as detailed in Annex B of the report and also in the Capital Programme attached at Annex A of the report;

 

(2)     the increase of capital expenditure funded from the Economic Development Fund of £168,996;

 

(3)     the funding allocation to the Capital Programme as detailed in paragraph 3.1 of the report; and

 

(4)     the Treasury Management position and prudential indicators at Annex E of the report.