90 Capital Programme Scheme Proposal Forms 2014/15 and Additional Schemes in 2013/14 PDF 176 KB
This report seeks approval of the Capital Programme Scheme proposal forms 2014/15 and additional schemes in 2013/14.
In accepting the recommendations, the capital programme scheme proposal forms 2014/15 detailed in Annex A1-A22 of the report will be approved for implementation in 2014/15; and the capital programme schemes in 2013/14 detailed at paragraph 1.4 and further detailed in Annex B1-B2 of the report will be approved for implementation in the current financial year 2013/14.
Minutes:
The subject of the decision:
This report sought approval of the Capital Programme Scheme proposal forms 2014/15 and additional schemes in 2013/14.
Alternative options considered:
None.
The reason for the decision:
Cabinet was satisfied that this would be an efficient use of Council resources and demonstrated value for money in the implementation of the individual schemes.
THE DECISION:
That Cabinet approves and recommends to Council:-
(1) the capital programme 2014/15 be increased by £141,000 to £2,126,350;
(2) the capital programme scheme proposal forms 2014/15 detailed in Annex A1-A22 be approved for implementation in 2014/15;
(3) the capital programme schemes in 2013/14 detailed at paragraph 1.4 of the report and further detail in Annex B1 be approved for implementation in the current financial year 2013/14; and
(4) the Prudential and Treasury Indicators attached at Annex C of the report be approved.