53 2018/19 Q3 Capital Monitoring and Treasury Management Report PDF 69 KB
This report provides an update at Quarter 3 as at 31 December 2018 on the progress on the capital programme 2018/19 and the treasury management position. A full schedule of the capital programme 2018/19 schemes is attached at Annex A of the report, together with the relevant update on progress of each scheme.
In accepting the recommendations, Cabinet will approve and recommend to Council the net increase of £857,047 in the capital programme to £15,331,211 as detailed in Annex B and also in the capital programme attached at Annex A of the report; the increase of capital expenditure is funded from earmarked reserves at £11,845,413 where £45,000 is from the Council Tax Payers Reserve Fund, £49,313 is from external grants/contributions and £11,751,100 is funded from surplus funds or borrowing; the funding allocation to the capital programme as detailed in paragraph 3.1 and 3.2 and the Treasury Management and Prudential Indicators at Annex E of the report.
Additional documents:
Minutes:
The subject of the decision:
This report provided the quarter 3 update at 31 December 2018 on the progress of the Capital Programme 2018/19 and the Treasury Management position. A full schedule of the Capital Programme 2018/19 schemes was attached at Annex A of the report, together with the relevant update on progress of each scheme.
Alternative options considered:
None.
The reason for the decision:
Capital expenditure was intrinsically linked with Treasury Management as the way that the Capital Programme was funded directly affected the Treasury Management arrangements of the Council.
THE DECISION:
That Cabinet approves and recommends to Council:-
(1) the net increase of £857,047 in the capital programme to £15,331,211 as detailed in Annex B and also in the capital programme attached at Annex A of the report;
(2) the increase of capital expenditure is funded from earmarked reserves at £11,845,413 where £45,000 is from the Council Tax Payers Reserve Fund, £49,313 is from external grants/contributions and £11,751,100 is funded from surplus funds or borrowing;
(3) the funding allocation to the capital programme as detailed in paragraph 3.1 and 3.2 of the report; and
(4) the Treasury Management and Prudential Indicators at Annex E of the report.