Distribution of Community Infrastructure Levy Receipts

06/12/2022 - Distribution of Community Infrastructure Levy Receipts

The subject of the decision:

 

This report provided an update on the Community Infrastructure Levy expenditure and reviewed the commitments to funding and a commentary on progress; considered any changes in commitments required; reviewed additional funding available for expenditure; and sought agreement to any new schemes.

 

Alternative options considered:

 

None.

 

The reason for the decision:

 

To comply with the requirements set out in national legislation and the Community Infrastructure Levy (Amendment) (England) (No 2) Regulations 2019.

 

The decision:

 

That Cabinet:-

 

(1)       reaffirms its commitment to provide Community Infrastructure Levy funding to the schemes and to the amounts previously approved as set out in Appendix A – column (d) of the report;

 

(2)       approves Community Infrastructure Levy  funding to the new schemes and to the amounts shown as set out in paragraph 2.5 and Appendix A – column (e) of the report, subject to recommendation 4;

 

(3)       delegates authority to allocate any remaining Community Infrastructure Levy funds, in accordance with the Council’s policies and subject to recommendation 4, to the Chief Executive in consultation with the Leader; and

 

(4)       the consent of North Yorkshire Council be sought for the expenditure in recommendations 2 and 3 under Section 24 of the Local Government and Public Involvement in Health Act 2007.